Select Page

Time and work wages and chain rule is one of the most important and frequently tested topics in quantitative aptitude for competitive exams. It is asked in almost every major exam including CAT, SSC CGL, SSC CHSL, Bank PO, Bank Clerk, Railway RRB and CSAT. A strong understanding of time and work wages and chain rule concept, formulas and tricks is essential for scoring well in these exams. In this post we cover three major subtopics. First is time and work which covers the basic definition of efficiency and work formula, three methods of solving problems — LCM method, percentage method and fraction method, ratio of efficiencies of two or more persons, and problems when persons leave work in between from beginning or from end. Second is wages which covers how total payment is divided among workers always in the ratio of work done by each person and not in ratio of time spent. Third is chain rule which covers problems involving multiple variables like number of workers, number of days, hours per day and efficiency all changing simultaneously using the formula N1 × D1 × H1 × E1 = N2 × D2 × H2 × E2 — all explained with multiple methods and solved examples.

📚 What You Will Learn in This Post

⏱ Time and Work

What is Efficiency — Work Formula and Efficiency Definition

LCM Method, Percentage Method and Fraction Method

Ratio of Efficiencies — When Two or More Persons Work Together

Persons Leaving Work in Between — From Beginning and From End

Complex Problems — Scheduled vs Actual Time Using Alligation Method

💰 Wages

Wages Division — Always in Ratio of Work Done by Each Person

🔗 Chain Rule

Chain Rule Formula — N × D × H × E = Constant Work

Chain Rule Solved Examples — Workers Days Hours and Efficiency

Time & Work, Wages, Chain Rule

Work = Time × Efficiency

∴ efficiency = \(\frac{{work}}{{time}}\)
So we can say that work done in unit time by a person is called the efficiency of that person.
Hence, efficiency ∝ work
& efficiency ∝ \(\frac{1}{{time}}\)
So if A can complete a work in t₁ time
& B can completer a work in t₂ time 
then \(\frac{{{A_{Eff.}}}}{{{B_{Eff.}}}} = \frac{{{t_2}}}{{{t_1}}}\)
● Problems can be solved by following three approaches as per given data value:

Time & WorkLCM MethodPercentage MethodFraction MethodTotal Work60A20B30time tocompleteworkLCM of(20, 30)32EffEff∴ tABTotal Work100%A10B50time tocompletework10%20%Find 60% work will be donein how much time(A + B) work = 10% + 20% = 12%∴ time taken by (A+B) to do 60% of work = = 5 daysA B26 days 17 daystime tocompleteworkA goes aftercompleting halfof the work.∴ Remaining workwill be completed byB in 17× = 85 days

● LCM Method:

xyzABCxdayszdaysydaysyzxyzxABC

\({A_{eff}} = \frac{{Total\;Work}}{{time\;to\;complete\;total\;work\;by\;A}}\)
Similar for \({B_{eff}}\) & \({C_{eff}}\)
So we can say work done in unit time by A, B or C is called its efficiency.

A Bx days y days y : xTime taken to complete the workRatio of efficiency of A & BA B Cx days y days z days yz : zx : xy : : Time taken to complete the workRatio of efficiencyRatio of efficiency

because efficiency is inversely proportional to time taken to complete the work.

Chain Rule:-

Example formula:

because the job of engine is to work coal.

● No. of Examiner₁ × days₁ × work rate₁ × efficiency₁ = No. of Examiner₂ × days₂ × work rate₂ × efficiency₂

(Q). A can complete \({\frac{2}{5}^{th}}\) of a work in 1 day. In how many days he can complete the same task.
Sol:
∴ \({A_{eff}} = \frac{2}{5}\)
time taken by A to complete the job = \(\frac{1}{{{A_{eff}}}} = \frac{5}{2}\) = 2.5 days              Answer

(Q). A can complete a job in 10 days, B can do the same job in 20 days. In how many days working together they can complete the job.
Sol:

20AB21Answer

(Q). A can do a piece of job in 10 days. B can do it in 15 days & C can do it in 20 days. In how many days A, B and C can complete the whole work working togethers.
Sol:-

60AB63Answer4C101520

● If persons are leaving the work in between the completion of whole work:
    ⟹ whoever leaves the work from forward, he is marked minus and becomes absent to calculate complete time of completion of work
    ⟹ whoever leaves the work from behind, he is marked plus and becomes present to calculate complete time of completion of work.

(Q). A can do a work in 20 days and B can do it in 30 days. If A & B started working together but A left th job after 8 days. Find the time taken to complete the remaining job by B & overall time to complete the job.
Sol:

60A32C2030

total work = 60
total work 8 days of (A + B) = 8 + (3 × 2)

= 40
Remaining work = 60 – 40 = 20
∴ time taken by B to do the Remaining job = \(\frac{{20}}{2}\)
10 days                    Answer
overall time to complete the work = 8 + 10 = 18 days                   Answer

Alternate:
∴ time taken to complete work = \(\frac{{60 – 8 \times 3}}{2}\) = 18 days                Answer
∴ B worked for 18 – 8 = 10 days       Answer

A + B8 daysAB

(Q). A can do a job in 20 days & B can do it in 30 days. If A & B started working together but B left th job 5 days before completion. Find the time taken to complete the job.
Sol:-

60A32C2030A + BBA5 days

5 days work of A = 5 × 3 = 15
∴ remaining work which will be done by A & B together = 60 – 15 = 45
combined efficiency of A & B = 3 + 2 = 5
∴ time taken by A & B to do combined work = \(\frac{{45}}{9}\) = 9 
∴ total time to complete the job = 9 + 5 = 14 days              Answer

Alternate:
time to complete job = \(\frac{{60 + 5 \times 2}}{{3 + 2}}\) = 14 days             Answer

A A + B Bx + a x x + btime to complete workthen

(Q) Two workers A & B are engaged to do a piece of work. A working alone would take 12 hours more than they working together. If B worked alone, he would take \(1\frac{1}{3}\) hours more than when worked together. Find the time required to finish the work together ?
Sol:-

A A + B Bx + 12 x x + time to complete work∴ x = = 4 hours Answer

(Q). A and B are equally efficient, and each could individually complete a piece of work in 30 days. A & B started working together but A took ‘a’ days off after every four days of work while B took ‘a’ days off after every five days of work. If they started work on 01 august, 2022, on which date was the work completed ?
Sol:
If A & B would not have taken any leave then the work would have been completed in \(\frac{{30}}{2}\) = 15 days
But A & B are taking leaves after working few days so time taken will be more than 15 days.
Now in these 15 days A’s leaves = \(\left[ {\frac{{15}}{4}} \right]\) = 3
& in these 15 days B’s leave = \(\left[ {\frac{{15}}{5}} \right]\) = 3
B will take 3ʳᵈ leave after work completion so its 3ʳᵈ leave will not be counted
So B’s leaves will be counted 2
but since A & B are working together so work will be finished at the same time for A & B
So higher of A’s leaves & B’s leaves will be counted
Hence total time to complete the work as per described condition = 15 + 3 = 18 days       Answer
∴ work will be completed in 18 august2022          Answer
Note: the person who is taking higher of the leaves ⟹ its leaves are added

(Q). A & B individually can do some work in certain number of days. A & B completed a work together. If A started the work 4 days later than the scheduled time & B started the work 13 days earlier than the scheduled time then the work would be completed 5 days earlier. What is the time taken by A to complete the work alone if B completes the work in 24 days.
Sol:
Concept:
When alligation method is applied on time we get ratio of efficiencies.

A B+ 4 - 13 8 : 9-5effTime9 : 18×327 days Answer
Actualstart of BActualstart of A13 days4 daysScheduledstartshould havebeen stop of B8 days5 days4 days9 days13 daysActualStopScheduledStopshould havebeen stop of AMethod(2):

A & B started working together & work completes 5 days earlier than the scheduled time.
If we consider only A then work would have been completed 4 days late than the scheduled time but it completed 5 days earlier than scheduled time.
∴             A
time ⟹ 5 + 4
= 9
Similarly, If we consider only B then work would have been completed 13 days earlier than the scheduled time but it completed 5 days earlier than the scheduled time.
∴             B
time ⟹ 13 – 5
= 8

A Btime ⟹ 9 824×327 days Answer

● wages will be divded into the ratio of their work done.

❓ Frequently Asked Questions on Time and Work

Q1. What is efficiency in time and work?

Efficiency is the amount of work done by a person in unit time. The formula is Work = Time × Efficiency which means Efficiency = Work divided by Time. Efficiency is directly proportional to work done and inversely proportional to time taken. If A can complete a work in t1 days and B can complete it in t2 days then ratio of their efficiencies = t2 : t1. This is a fundamental concept in time and work problems asked in CAT, SSC CGL, Bank PO and Railway exams.

Q2. What is the LCM method in time and work?

In the LCM method we take the total work as the LCM of the individual times taken by each person. Then efficiency of each person = Total Work divided by their individual time. For example if A takes 20 days and B takes 30 days then total work = LCM(20,30) = 60 units. Efficiency of A = 3 units per day and B = 2 units per day. Time taken by A and B together = 60 divided by 5 = 12 days.

Q3. How to solve problems when a person leaves work in between?

When a person leaves work from the beginning they are marked minus and become absent for calculating completion time. When a person leaves work from the end they are marked plus and are considered present. For example if A and B start together and A leaves after 8 days then calculate work done in 8 days by both then find remaining work and divide by B’s efficiency to get remaining time.

Q4. What is the chain rule in time and work?

The chain rule states that Number of workers × Days × Hours per day × Efficiency = Constant work. When any of these variables change we can find the unknown variable by keeping work constant. The formula is N1 × D1 × H1 × E1 = N2 × D2 × H2 × E2. This rule is very useful in problems involving multiple variables like workers, days, hours and efficiency together.

Q5. How are wages divided in time and work problems?

Wages are divided among workers in the ratio of work done by each of them. Work done = Efficiency × Time worked. So if A works for more days or has higher efficiency then A gets a proportionally higher share of the wages. For example if A and B work for different number of days then calculate total units of work done by each and divide wages in that ratio.

Q6. What is the formula when A and B together take x days and individually take different times?

If A working alone takes (x + a) days and B working alone takes (x + b) days and together they take x days then x = square root of (a × b). For example if A alone takes 12 hours more than together and B alone takes 4/3 hours more than together then time together = square root of (12 × 4/3) = 4 hours.

Q7. Which competitive exams cover time and work questions?

Time and work is asked in almost every competitive exam including CAT, SSC CGL, SSC CHSL, Bank PO, Bank Clerk, Railway RRB, CSAT and all state level competitive exams. It is closely related to Pipe and Cistern and Time Speed and Distance concepts.

Q8. Where can I practice time and work questions?

After understanding the concept you can practice on our Time and Work Exercise page which contains a large number of solved practice questions covering all types of time and work problems asked in competitive exams. You can also check our Pipe and Cistern Concept page for related topics.

Q9. What is wages in time and work?

Wages is the total payment distributed among workers based on the amount of work done by each of them. Wages are always divided in the ratio of work done by each person and not in the ratio of time spent working. Work done by each person = Efficiency × Number of days worked. This is a very important distinction that is frequently tested in competitive exams like CAT, SSC CGL, Bank PO and Railway RRB.

Q10. How to divide wages when persons work for different number of days?

When persons work for different number of days first calculate work done by each person using Work = Efficiency × Days worked. Then divide the total wages in the ratio of work done. For example if A has efficiency 3 and works 10 days then work done = 30 units. If B has efficiency 2 and works 15 days then work done = 30 units. So wages are divided equally in ratio 1:1 between A and B.

Q11. What is the difference between wages ratio and time ratio?

Wages ratio is based on work done by each person which equals efficiency multiplied by days worked. Time ratio is simply the ratio of number of days each person worked. These two ratios are different when persons have different efficiencies. Always use work done ratio and never use time ratio for dividing wages. This is one of the most commonly made mistakes in competitive exam wage problems.

Q12. What is chain rule and when is it used?

Chain rule is used when multiple variables like number of workers, number of days, hours per day and efficiency are all changing simultaneously in a problem. The formula is N1 × D1 × H1 × E1 = N2 × D2 × H2 × E2 where work done on both sides remains constant. Chain rule is very useful in problems like if 10 workers complete a work in 5 days working 8 hours per day then how many days will 8 workers take working 10 hours per day to complete the same work.

Q13. How to apply chain rule with more than two variables?

To apply chain rule with more than two variables write all known values on left side and unknown on right side keeping work constant. Direct variables like workers and days are written directly. Inverse variables like efficiency are written in inverse position. The formula N1 × D1 × H1 × E1 = N2 × D2 × H2 × E2 covers all cases. Simply substitute known values and solve for the unknown variable.

Q14. Where can I practice time and work wages and chain rule questions?

After understanding the concept you can practice on our Time and Work Wages and Chain Rule Exercise page which contains a large number of solved practice questions covering all types of problems asked in competitive exams. You can also check our Ratio and Proportion Concept which helps in understanding efficiency ratios better and our Percentage Concept which is useful for the percentage method of solving time and work problems.